Seeq Summit Perth 2026 – Real-Time Predictive Models for Cracker Run Length – Natchanon Naruesatyan & Pattama Poorahong (TPC).pdf

©2024 – Seeq Corporation | 1©2024 – Seeq Corporation | 1
Natchanon Naruesatyan / Pattama Poorahong Focused Improvement Engineer
Real-Time Predictive Models
for Cracker Run Length
Thai Plastic and Chemicals Public Company Limited (TPC)
TPC Group’s Company Profile
VIETNAM
PVC Resin PVC compoundTHAILAND
PVC resin & VCM Research center
INDONESIA PVC Resin
Pipes & Fittings
4
PVC Resin
VCM
Manufacturing Sites:
PVC Compound Established: since 1966
TPC Supply Chain Diagram
Olefin Plant
Ethylene
EDC
PVC Plant
Marine
Packaging type
Tank car Flexible Bag
PVCVCM
VCM Plant (Vinyl Chloride Monomer) (Poly Vinyl Chloride)
Sea Bulk
Customers
PP Woven Bag
PVC Finish Goods VCM = Vinyl Chloride Monomer
EDC = Ethylene Di-Chloride HCl = Hydrogen Chloride PVC = Poly Vinyl Chloride
VCM Process Flow Diagram
VCM = Vinyl Chloride Monomer
EDC = Ethylene Di-Chloride HCl = Hydrogen Chloride PVC = Poly Vinyl Chloride
EDC Cracking
EDC
HCI
VCM
Fuel Gas
Temperature
Productivity
Coke Formation
Run length
Cracking Operating Trade-offs:
IMPORTED EDC
Challenge
Cracker run length dictates our shutdown schedule
The challenge is moving from guesswork to precision
The ability to predict the exact shutdown date is crucial. It allows us to:
• Enable effective maintenance planning • Maximize productivity and eliminate profit loss from early shutdowns
Without real-time data, we are trapped:
• By Ineffective SD Planning:
• By a High-Stakes Trade-Off:
Previous Attempts
●Manual Process: Run length projections are manually calculated by
engineers using PI data exported to Excel
● Labor-Intensive: The process is time-consuming and requires
significant manual intervention for each update
● High Volatility: Forecasts fluctuate frequently with operational
changes, requiring constant recalculations to remain
accurate and reliable
Export PI
data to
Excel
Cleansing
data Regression Forecast Report
Seeq Solution
Export PI
data to
Excel
Cleansing
data Regression Forecast Report
Real-time auto update / Online Visual / Notification
Results
Automated,
Real-Time Forecasting
Replaces slow, manual Excel calculations with
a dynamic forecast that updates every 1
hour while achieving a predictive accuracy of over 80%
Enhanced Online Visibility
& Collaboration
Provides a shared, interactive dashboard
for all teams (Operations, Maintenance) to align on one consistent forecast for faster
decision-making.
Proactive Notification
& Alerting System
Automatically notifies teams before a
shutdown is required, shifting maintenance
from a reactive emergency to a planned,
proactive event
Next Challenge
This success led us to ask a next bigger question:
“What if we could do more than just Predict the shutdown?
and What if we could actually Control it?”
Perform correlation analysis
Modeling & Forecasting
Create A Prescriptive Model
Y= f(X1,X2,X3,…,Xn)
Prediction Prescription
Two fundamental questions:
1. What are the Key operational factors that directly accelerate the need for a shutdown?
2. How can we adjust these factors in real-time to Safely extend our run length?
TPC Slide 1 Slide 2 Slide 3 Slide 4 Slide 5: TPC Supply Chain Diagram Slide 6 Slide 7 Slide 8 Slide 9 Slide 10 Slide 11